PHASE I SEWER EXPANSION PROJECT
Sewer construction detours and traffic management plans are updated regularly on this page.
Updates can also be tracked via mobile device using the Waze app or Google maps.
CONSTRUCTION THIS WEEK
Strawberry Hill Road Sewer Expansion Project Construction Schedule –
Weekly Update
Figure 1: Anticipated Sewer Work Area August 8, 2022 to August 12, 2022
The Strawberry Hill Road Sewer Expansion Project is ongoing with construction schedule update as outlined below.
Week of 8-15-2022 to 8-19-2022
- Sewer main installation on Wequaquet Lane from Strawberry Hill Road to Phinney’s Lane.
- Pump station site work at 528 Craigville Beach Road property easement. Construction access and work will occur on section of parcel fronting Strawberry Hill Road.
- Road closure and detour will be in place, with resident and business access only.
Week of 8-22-2022 to 8-26-2022
- Sewer main installation on Wequaquet Lane from Strawberry Hill Road to Phinney’s Lane.
- Pump station site work at 528 Craigville Beach Road property easement. Construction access and work will occur on section of parcel fronting Strawberry Hill Road.
- Road closure and detour will be in place, with resident and business access only.
All closed roadways will remain accessible to residents and businesses throughout construction. As always, please slow down and use extreme caution when traveling through the road construction areas, and follow posted safety and detour signs.
If you have any questions or wish to receive project updates, please contact Paul Ruszala, P.E., Senior Project Manager, at the Department of Public Works at 508-790-6400 orpaul.ruszala@town.barnstable.ma.us.

COMING SOON: HOMEOWNER GUIDE TO SEWER CONNECTION
CWMP News Updates
CAPE COD AND ISLANDS WATER PROTECTION FUND 2021 ANNUAL REPORT
The Cape Cod and Islands Water Protection Fund (CCIWPF) was established by the Massachusetts Legislature in 2018 (M.G.L. Chapter 29C, Section 19) to help Cape Cod and Islands towns pay for necessary wastewater infrastructure and water quality remediation projects....
Route 28 East Sewer Expansion Project Moves Forward
The Route 28 East project will allow approximately 90 properties to connect to the municipal sewer system and will install critical infrastructure needed to proceed with other Phase 1 sewer expansion projects. This project will expand sewer westerly along Route 28 to...