Centerville Village Sewer Expansion Project - North Phase
Phase
1
Construction Start
Fall 2024
Construction End
Spring 2027
(Anticipated)
Hover over each tile to learn more!
Number of Properties Anticipated to be Sewered
219
Anticipated Nitrogen Removal
5.7 Kg/day
Miles of Sewer
4
Update as of 10/21/26
Construction continues in the following areas:
- Mother’s Park Area
- (Overnight Work) Route 28, from Old Stage Road to Phinney’s Lane
Additional work, including testing and pump station installation, is ongoing along Shootflying Hill Road.
Project Overview
In March 2024, the Town Council approved the recommendation to split the Centerville Village Sewer Expansion Project into a North Phase and a South Phase.
This project will expand sewer to properties along the following areas:
- Route 28, from Phinney’s Lane to Old Stage Road
- Phinney’s Lane, from Route 28 to Main Street
- Old Stage Road, from Route 28 to Shootflying Hill Road
- Shootflying Hill Road, from Old Stage Road to Service Road
This project is anticipated to install approximately four miles of sewer and will be a combination of gravity sewers and low-pressure sewers.
Three submersible pump stations are anticipated to be constructed for this project, located at:
- 567 Shootflying Hill Road (Town-Owned Parcel)
- 944 Shootflying Hill Road (Town-Acquired Easement)
- Mother’s Park (Includes removal of Mother’s Park Road, realignment of intersection, and park upgrades)
Public Informational Meetings
- October 1, 2024
The below presentations occurred prior to the decision to split the Centerville Village Sewer Expansion Project into two phases
- April 4, 2023
- March 14, 2023