Centerville Village Sewer Expansion Project-South Phase

Phase

1

Construction Start

January 2027
(Anticipated)

Construction End

Fall 2028
(Anticipated)

 

Hover over each tile to learn more!

Number of Properties Anticipated to be Sewered

160

Anticipated Nitrogen Removal

3.2 Kg/day

Miles of Sewer

2.5

Updates as of 10/19/26

Status: The construction contract has been awarded to C. Naughton Company. Construction is anticipated to be begin in early 2027. A Public informational meeting will be held on Wednesday, November 18, 2026 at 6:00 PM at the Barnstable Adult Community Center (825 Falmouth Road). Residents in the project area should expect to receive a mailing with additional details.

Please note, the construction contract prohibits construction from occurring on Main Street, Centerville (between Old Stage Road and South Main Street) prior to January 4, 2027.

Project Overview

This project will expand sewer services to 160 parcels south of Route 28, Centerville, including:

  • Old Stage Road, from Route 28 to Main Street (Centerville)
  • Main Street (Centerville), from Old Stage Road to South Main Street
  • Craigville Beach Road, from South Main Street to the Centerville River Bridge
  • Old Post Road, from Old Stage Road to Phinney’s Lane
  • Park Avenue, from Bacon Lane to Main Street (Centerville)
  • Bacon Lane, Linden Avenue, and Maple Avenue

Public Informational Meetings

Presentations which occurred prior to the decision to split the Centerville Village Sewer Expansion Project into two phases

Project Information

Click each image to open a full-size PDF Version

Banner page for Centerville Village Sewer Expansion Project – South Phase with town seal and 'Project at a Glance' heading
Map showing blue parcels for Centerville Village South SEP along Old Stage Road and South Main Street; includes legend, scale bar, compass, and title 'Centerville Village South Sewer Expansion Project' with subtitle 'Comprehensive Wastewater Management Plan'