Phinney's Lane Neighborhoods Sewer Expansion Project
Phase
1
Construction Start
January 4, 2027
Construction End
Late 2029
(Anticipated)
Hover over each tile to learn more!
Number of Properties Anticipated to be Sewered
563
Anticipated Nitrogen Removal
8.4 Kg/day
Miles of Sewer
8
Updates as of 11/03/2026
Status: The contractor has issued a schedule update, signaling an anticipated January 4, 2027 start-date.
The following roadways have been identified by the contractor to be under construction between January 2027 and March 2027:
- Crosby Road
- Pond Street
- Lake Drive and a portion of Juniper Road
- Brezner Lane
- Tellegen Trail
- Sail-A-Way
Property owners identified within this project should have received a Project Notification via Certified Mail, which contains additional information on the project and a Sewer Service Location Form. The form should be returned to the DPW as soon as possible.
Project Overview
This project will expand sewer into residential neighborhoods on the east and west side of Phinney’s Lane. By extending sewer service to these neighborhoods, the Town will help remove nitrogen from the Centerville River Watershed, helping the Town meet Total Maximum Daily Load (TMDL) requirements, while also addressing septic systems adjacent to Wequaquet Lake and upgradient of Long Pond, Centerville. Portions of the project are also located within Zone 2 wellhead protection areas, where protecting groundwater is particularly important for drinking water supplies.
The Town’s most recent Public Informational Meeting for this project was held on Wednesday, October 7, 2026. The meeting was recorded and available for viewing below, in addition to a copy of the presentation slides.
Public Informational Meetings
- Construction Public Informational Meeting – October 7, 2026
- Design Public Informational Meeting – March 11, 2026