Phase 1

Sewer Expansion Projects

Currently the Town is implementing Phase 1 (Years 0-10) of the Comprehensive Wastewater Management Plan (CWMP). Phase 1 consists of 18 individual sewer collection system projects, and additional sewer extensions, that will result in roughly 90 miles of new sewer infrastructure. Once complete, Phase 1 will remove approximately 44% of the nitrogen impacting our waters.

Scroll below for a detailed matrix of Phase 1 Project updates or utilize our Public CWMP Maps to locate your address and determine if/when your property may be recieving future sewer service as part of a sewer expansion project. 

Locate Your Property

Using the Public CWMP Map, search your address or parcel number to locate your property and determine if/when your property may be recieving future sewer service as part of a sewer expansion project. Scroll further down the page for additional detailed project status updates and links to important resources including public meeting recordings. 

 

↓ SCROLL DOWN TO VIEW PROJECT DETAILS ↓

Project Status & Construction Updates

Click through each sewer expansion project currently included within Phase 1 of the CWMP for a high-level summary, anticipated project timeline, and relevant construction updates.

Phase 1 Progress

%

Completed Sewer Connections

There are currently 308 properties available to connect to sewer as a result of the Town’s first two completed Phase 1 Sewer Expansion Projects. Of those eligible properties, 48% have completed their connection as of June 2025. 

Strawberry Hill Road Sewer Expansion

Status: Completed; Sewer Connections Available

Overview: This project expanded sewer along Strawberry Hill Road and Wequaquet Lane from Route 28 to Route 132. This involved the construction of approximately 20,500 Linear Feet (LF) of gravity sewer, 6,400 LF of force main, the replacement of approximately 4,000 LF of water main, and the installation of a new submersible pump station on a town-controlled easement at 528 Craigville Beach Road.

Properties Eligible to Connect to Sewer: 214

Anticipated Nitrogen Removal: 4.2 kg/day

Presentations:

Last Updated 06/25/2025

Route 28 East Sewer Expansion

Status: Completed; Sewer Connections Available

Overview: This project expanded sewer along Route 28 to the intersection of Route 28 and Phinney’s Lane. This involved the construction of approximately 11,000 Linear Feet (LF) of new sewer, 12,000 lF of sewer force main, and a pump station on town-owned property at 1456 Falmouth Road. This project also included modifications to the Water Pollution Control Facility (WPCF) to accommodate the new force mains.

Properties Eligible to Connect to Sewer: 94

Anticipated Nitrogen Removal: 1.8 kg/day

Presentations

Last Updated 06/25/2025

Centerville Village Sewer Expansion - North Phase

In March 2024, the Town Council approved the recommendation to split the Centerville Village Sewer Expansion Project into a North Phase and a South Phase.

Status: Active Construction

Overview: This project will expand sewer to properties along the following areas:

  • Route 28, from Phinney’s Lane to Old Stage Road
  • Phinney’s Lane, from Route 28 to Main Street
  • Old Stage Road, from Route 28 to Shootflying Hill Road
  • Shootflying Hill Road, from Old Stage Road to Service Road

This project is anticipated to install approximately four miles of sewer and will be a combination of gravity sewers and low-pressure sewers.

Three submersible pump stations are anticipated to be constructed for this project, located at:

  • 567 Shootflying Hill Road (Town-Owned Parcel)
  • 944 Shootflying Hill Road (Town-Acquired Easement)
  • Mother’s Park (Includes removal of Mother’s Park Road, realignment of intersection, and park upgrades)

Anticipated Completion: Spring 2027

Anticipated Sewered Properties: 219

Anticipated Nitrogen Removal: 5.7 kg/day

Presentations

Last Updated 06/25/2025

Centerville Village Sewer Expansion - South Phase

In March 2024, the Town Council approved the recommendation to split the Centerville Village Sewer Expansion Project into a North Phase and a South Phase.

Status: Design In Progress

Overview: This project will expand sewer along the southern section of the proposed Park City Wind project’s onshore duct route, including:

  • Main Street, Centerville, from Old Stage Road to South Main Street
  • Craigville Beach Road, from the Centerville River Bridge to Covell’s Beach
  • Old Stage Road, from Route 28 to Main Street, Centerville
  • South Main Street, from Craigville Beach Road to Church Hill Road
  • Church Hill Road

This project is anticipated to install approximately 2.5 miles of sewer.

Anticipated Construction Start: Fall 2026

Anticipated Construction End: 2027

Anticipated Sewered Properties: 151

Anticipated Nitrogen Removal: 3.2 kg/day

Presentations:

Last Updated: 06/25/2025

Route 28 West Sewer Expansion

Status: Contract Award in Progress

Overview: This project will expand sewer to properties along the following areas:

  • Route 28 from Phinney’s Lane to Route 149
  • Old East Osterville Road
  • Oldham Road
  • Portions of Osterville-West-Barnstable Road
  • Bumps River Road

This project serves as the backbone of the CWMP’s westerly expansion, allowing access into the Three Bays and Popponesseset Bay Watersheds. This project will also see the decommissioning of the Marstons Mills Wastewater Treatment Plant, transferring the service area to the Water Pollution Control Facility (WPCF).

This project is anticipated to install approximately five miles of sewer.

Anticipated Construction Start: Fall 2025

Anticipated Construction End: 2028

Anticipated Sewered Properties: 230

Anticipated Nitrogen Removal: 4.9 kg/day

Presentations:

Last Updated 06/25/2025

Phinney's Lane Neighborhoods Sewer Expansion

Status: Design in Progress

Overview: This project will expand sewer into the residential neighborhoods on the east and west side of Phinney’s Lane, which will tie into the sewer infrastructure constructed along Phinney’s Lane as part of the Strawberry Hill Road and Route 28 East projects.

In this area, existing on-site solutions to address wastewater needs negatively affect Lake Wequaquet and the Centerville River.

This project is anticipated to install approximately 8 miles of sewer.

Anticipated Construction Start: 2026

Anticipated Construction End: 2029

Anticipated Sewer Properties: 587

Anticipated Nitrogen Removal: 8.2 Kg/day

Last Updated 06/25/2025

Long Pond Area Sewer Expansion

Status: Design in Progress

Overview: This project will expand sewer to the south of Route 28, around Long Pond, Centerville.

In this area, existing on-site solutions to address wastewater needs negatively affect Long Pond. Additionally, this project will sewer Centerville Elementary School.

This project is anticipated to install approximately 9.7 miles of sewer.

Anticipated Construction Start: 2027

Anticipated Construction End: 2030

Anticipated Sewered Properties: 554

Anticipated Nitrogen Removal: 10.3 kg/day

Last Updated 06/25/2025

Long Beach Area Sewer Expansion

Status: Design in Progress

Overview: This project will expand sewer to properties near the following areas:

  • Craigville Beach
  • Long Beach
  • Short Beach
  • Lake Elizabeth

In this area, existing on-site solutions to address wastewater needs negatively affect Centerville River, Lake Elizabeth, Red Lily Pond, Craigville Beach, Covell’s Beach, and Long Beach. This project also includes the decommissioning of the existing shared septic system near Lake Elizabeth.

Anticipated Construction Start: 2027

Anticipated Construction End: 2029

Anticipated Sewered Properties: 227

Anticipated Nitrogen Removal: 3.6 kg/day

Last updated 06/25/2025

Great Marsh/Shootflying Hill Road Neighborhoods Sewer Expansion

Status: Preliminary Design in Progress

Overview: This porject will expand sewer to properties on Great Marsh Road, a portion of Shootflying Hill Road, and to the neighborhoodsadjacent to those roads.

In this area, existing on-site solutions to address wastewater needs negatively affect Lake Wequaquet.

This project is anticipated to install approximately seven miles of sewer.

Anticipated Construction Start: 2028

Anticipated Construction End: 2031

Anticipated Sewered properties: 466

Anticipated Nitrogen Removal: 6.2 kg/day

Last updated 06/25/2025

Old Yarmouth Road Sewer Expansion

Status: Preliminary Design in Progress

Overview: This project will expand sewer to the north of Route 28 and east of Yarmouth Road, providing sewer to businesses and residents along the following roads:

  • Old Yarmouth Road
  • Yarmouth Road
  • Joaquim Road
  • Bodick Road
  • Rosary Lane
  • Ferndoc Street
  • Route 28 from Cedar Street to Town Line

In this area, existing on-site solutions to address wastewater needs negatively impact economic development. Additionally, the Hyannis Water Syster Maher Drinking Water Wells, directly adjacent to the project area, have experienced contamination over the years.

This project is anticipated to install approximately 2.5 miles of sewer.

Anticipated Construction Begin: 2028

Anticipated Construction End: 2030

Anticipated Sewered Properties: 131

Anticipated Nitrogen Removal: 2.3 kg/day

Last updated 06/25/2025

Huckins Neck Sewer Expansion

Status: Preliminary Design and Survey Anticipated in 2027

Overview: This project will expand sewer to properties located on Huckins Neck, adjacent to Lake Wequaquet, Shallow Pond, and Bearse Pond.

In this area, existing on-site solutions to address wastewater needs negatively affect Lake Wequaquet, Shallow Pond, and Bearse Pond.

This project is anticipated to install approximately 2 miles of sewer.

Anticipated Construction Begin: 2029

Anticipated Construction End: 2031

Anticipated Sewered Properties: 147

Anticipated Nitrogen Removal: 2.1 kg/day

Last updated 06/25/2025

Prince Cove Sewer Expansion

In October 2024, the South County Road Sewer Expansion Project was integrated into the Prince Cove Sewer Expansion Project.

Status: Preliminary Design and Survey Anticipated in 2027

Overview: This project will expand sewer to properties on the north and east sides of Prince Cove.

This area has been identified as a needs area for nitrogen removal by Massachusetts Estuaries Project (MEP) modeling.

This project is anticipated to install approximately 7.5 miles of sewer.

Anticipated Construction Start: 2029

Anticipated Construction End: 2031

Anticipated Sewered Properties: 333

Anticipated Nitrogen Removal: 8.0 kg/day

Last Updated 06/25/2025

Old Craigville Road Sewer Expansion

Status: Preliminary Design in Progress

Overview: This project will expand sewer to properties located on Old Craigville Road and adjacent neighborhoods.

In this area, existing on-site solutions to address wastewater needs negatively affect Red Lily Pond and Lake Elizabeth. Additionally, the northern portions of the project area have been identified as needs area for nitrogen removal by Massachusetts Estuaries program (MEP) modeling as well as drinking water well protection (COMM Water Supply Wells).

This project is anticipated to install approximately 6.6 miles of sewer.

Anticipated Construction Start: 2030

Anticipated Construction End: 2032

Anticipated Sewered Properties: 440

Anticipated Nitrogen Removal: 4.9 kg/day

Last updated 06/25/2025

Osterville Woods Sewer Expansion

Status: Preliminary Design and Survey Anticipated in 2027

Overview: This project will expand sewer to properties in the Osterville Woods neighborhoods and adjacent areas.

The western portion of the project area has been identified as a needs area for nitrogen removal by Massachusetts Estuaries Program (MEP) modeling. The entire project ahs been identified as a needs area for drinking water well protection as the project area is located within the Zone II to COMM water supply wells.

This project is anticipated to install approximately 3.8 miles of sewer.

Anticipated Construction Start: 2030

Anticipated Construction End: 2032

Anticipated Sewered Properties: 253

Anticipated Nitrogen removal: 4.7 kg/day

Last updated 06/25/2025

Lumbert Mill Sewer Expansion

Status: Preliminary Design and Survey Anticipated in 2028

Overview: This project will expand sewer to properties in the vicinity of Lumbert Mill Road and Route 28.

Anticipated Construction Start: 2031

Anticipated Sewer End: 2032

Anticipated Sewer Properties: 568

Anticipated Nitrogen Removal: 8.6 kg/day

Last updated 06/25/2025